Stage completion matrix

Percentage complete by process · updated 09:40

OrderBuyer / style KnitDyeCut PrintEmbSew FinishQCPack Ex-factoryRisk
PO-2048 NorthStarPOLO-2048 · 10,000 10010084 829174 696866 24 Aug
PO-2051 UrbanCoTSHIRT-1024 · 24,000 1007670 ——62 585648 28 Aug
PO-2062 BluePeakHOOD-3021 · 6,500 1008862 18—38 12100 30 Aug
PO-2057 ModeLineJOGGER-4421 · 8,200 10010096 —10081 747268 30 Aug
PO-2044 GlobalFitSHORT-2231 · 12,000 100100100 100—100 969488 19 Aug
PO-2053 Urban ThreadSWEAT-1288 · 5,400 1008254 22—41 282618 04 Sep
PO-2059 NorthStarSWEAT-1288 · 6,200 6422— ——— ——— 14 Sep
Blank cells mean the process does not apply to that style 7 of 64 orders in production shown

Sewing line loading — next 14 days

LineCurrent orderDaily outputBalance pcsDays neededFree from
Line 04PO-20486401,7802.820 Aug
Line 07PO-20485408001.519 Aug
Line 01PO-20511,1809,1207.726 Aug
Line 02PO-20511,1208,4007.526 Aug
Line 05PO-20577601,5582.119 Aug
Line 09PO-20624204,0309.628 Aug
Line 12Idle — changeover0——Available now
18 of 20 lines runningOpen production planning →

Bottleneck of the day

Cutting

Cutting is starving two sewing lines because navy fabric for PO-2048 is still with the dyeing vendor.

Waiting fabric
640 kg navy
Blocked pieces
1,600 pcs
Vendor
Sri Tex Processors
Promised
19 Aug 2026
Days late
6 days
Open job work order