Tasks total
20
10 done · 4 running
Completed on time
6
60% of closed tasks
Late tasks
3
Cutting, printing, embroidery
Critical path slip
+5 days
Against original plan
Days to ex-factory
7
24 Aug 2026

Critical path

Planned vs actual, every milestone owned by a person

TimelineGantt
Task Planned Actual Delay Owner Status
Order confirmationMerchandising 12 Jun12 Jun —Karthik S Done
Tech pack release v3Merchandising 16 Jun15 Jun −1 dKarthik S Done
Yarn booking — PO to spinnerPurchase 20 Jun22 Jun +2 dMohan R Done
Lab dip approvalMerchandising 26 Jun28 Jun +2 dKarthik S Done
Yarn in-houseStores 30 Jun02 Jul +2 dSelvam K Done
PP sample approvalSampling 04 Jul09 Jul +5 dDivya R Done
Knitting complete — 5,000 kgKnitting 08 Jul09 Jul +1 dRamesh P Done
Dyeing complete — lot DYE-2048Job work · ABC Dyeing 18 Jul21 Jul +3 dRamesh P Done late
Fabric QC & shade checkQuality 21 Jul23 Jul +2 dAnitha P Done
Cutting startCutting 24 Jul26 Jul +2 dVignesh M Done
Cutting complete — 10,000 pcsCutting · 8,400 done 02 Aug— +15 dVignesh M Late
Printing completeJob work · Kaveri Printing 06 Aug— +11 dSuresh M Late
Embroidery complete — 4,000 pcsJob work · Prime Embroidery 08 Aug— +9 dSuresh M Late
Sewing — 10,000 pcsSewing lines 04 & 07 20 Aug74% At riskBala S Running
FinishingFinishing bay 2 22 Aug69% —Bala S Running
Final inspection — AQL 2.5Quality 23 Aug— —Anitha P Planned
Packing complete — 100 cartonsPacking 24 Aug66% —Packing bay Planned
Ex-factoryLogistics 24 Aug— —Deepa V Planned
Vessel sailing — TuticorinLogistics 26 Aug— —Deepa V Planned
Delivery at destinationDubai, UAE 30 Aug— —Deepa V Planned
20 tasks · baseline set 12 Jun 2026 · last recalculated today 06:00 Open order control tower →

Where the 5 days went

PP sample approval5 d
Dyeing at ABC Dyeing3 d
Yarn booking2 d
Lab dip approval2 d
Fabric QC re-check2 d

Delays overlap; net slip on the critical path is 5 days, not 14.

Recovery options

  • Add second sewing line (line 07)+540 pcs/day · ₹0.42L overtimeApplied
  • Split shipment — 6,600 pcs nowBuyer approval requiredProposed
  • Air-freight balance 3,400 pcs₹3.80L extra freightLast resort