New Order Approvals Notifications Help RK Rajesh Kumar
Managing Director

Good morning, Rajesh

Monday, 17 August 2026 · Factory Operations Overview

Shift A live · updated 09:42
Today Month Season
Full analytics

Order spotlight — PO-2048 · NorthStar Apparel

POLO-2048 · 10,000 pcs · ₹38,00,000 · ex-factory 24 Aug · delivery 30 Aug 2026

Delivery risk Open TNA Control tower
✓Order12 Jun
✓Material28 Jun
✓Knitting5,000 kg
!Dyeing4,820 kg · 3 d late
✓Fabric QC4,109 kg
✓Cutting8,400 pcs
✓Printing8,180 pcs
●Sewing7,420 pcs
Finishing6,940 pcs
Final QC6,820 pcs
Packing66 cartons
Dispatch30 Aug
Order progress

74% complete · 7,420 of 10,000 pcs sewn

Days to ex-factory

7 days

2,580 pcs still to sew — needs 430 pcs/day

Projected margin

11.58%

Quoted 22.1% · see erosion

Blocking issue

Dyeing lot DYE-2049 held at Sri Tex Processors

1,600 pcs of cutting waiting on 640 kg navy

Produced today · all factories
38,640PCS
Target 42,000 pcs · 3,360 pcs behind plan
Target attainment
92%
Yesterday 89%
021,00042,000 pcs
Sewing lines running
18 / 20
Operators on floor
1,248
Rejection today
1.9%
Overtime hours
214

Revenue trend

▲ 8.4%
9.20APR
10.40MAY
11.10JUN
11.85JUL
12.84AUG

Invoiced value in ₹ Crore

Cash position

Receivables
₹2.84 Cr
Payables
₹1.92 Cr
Bank balance
₹84.2L
Overdue > 60 days
₹42.0L
Month profit
₹1.86 Cr
Open finance